Case: Greens Bayou waste site
Source: Historical releases from chemical manufacturing facilities
located in the vicinity of Greens Bayou
Release:
-
Heavy metals
-
DDT and metabolites (DDD, DDE)
Status:
The injury assessment has been completed for the Greens Bayou site. Paralleling
TCEQ’s remedial investigations for the Site, NOAA and DOI joined with the State
Trustees in an effort to assess the natural resource injuries and service
losses attributable to hazardous substances releases at the Site. The Trustees
determined that two categories of injury resulted at the Greens Bayou Site,
injury to bayou sediments and injury to terrestrial forested
wetlands/grasslands. Approximately 6.9 acres of benthic habitat in Greens Bayou
were impacted by hazardous substances historically released from the Site. This
area and approximately 12.4 acres of additional benthic habitat will likely be
impacted by the remedial actions at the Site. The creation of the Confined
Dredge Disposal Facility to manage sediments dredged as part of the remedial
activities will result in the destruction of approximately 33.6 acres of wooded
wetlands and grassland habitats. The work undertaken by the agencies indicated
that construction of 10.9 acres of vegetated intertidal wetlands and
preservation of 100 acres of forested wetland in the upper Galveston Bay,
Buffalo Bayou, or San Jacinto River watersheds would be needed to compensate
for these injuries and losses.
On the basis of this information, the Trustees
negotiated a settlement of state and federal natural resource damage claims
related to the Site in which the PRPs would implement marsh construction and
forested wetland preservation projects. On April 3, 2013, the court entered the Consent Decree to finalize the settlement.
|
|

|