|
|

|
Restoration Activities
Case: Elliott Bay/Duwamish River, WA
At this point in time, natural resource damage assessment (NRDA) restoration is
being conducted under a consent decree with the City of Seattle and King
County. Briefly, the Elliott Bay/Duwamish River Restoration Program (EB/DRRP)
was established to implement the sediment remediation, habitat development, and
source control provisions of that settlement. It is anticipated that future
settlements as a result of the assessment process being conducted by U.S.
Environmental Protection Agency (EPA) as well as other Trustee efforts will
result in additional NRDA restoration projects in the Elliott Bay environment.
Restoration Summary
The Concept Document summary and the two addenda
provide some background information on the Program and the evaluation and
ranking of potential remediation and habitat development sites. At this time,
all sediment remediation and habitat development projects under the Program
have been completed, except for monitoring activities which are on-going.
- Pier 53/55 Sediment Cap. Twenty-two thousand cubic yards of clean sand
were placed, one to three feet thick, on 4.5 acres of contaminated bottom
sediments offshore of Piers 53, 54, and 55, along Seattle's downtown
waterfront. Contamination consisted of a number of chemicals and metals.
Monitoring results indicate that the cap is stable and isolating contaminated
sediments as designed. See fact sheet
.
-
Norfolk Combined Sewer Overflow (CSO) Sediment Remediation
Project. This CSO is located near the south end of Boeing
Field. The sediments around the outfall contained high levels of contaminants,
including mercury, bis (2-ethylhexy) phthalate, and PCBs. Remediation of this
site began in February 1999 and was completed in March 1999. Contaminated
sediments were dredged, and the dredged area was backfilled with clean
sediment. A total of 5,190 cubic yards of sediment were removed.
-
Diagonal/Duwamish Combined Sewer Overflow. This site is located on the
east side of the Duwamish River, upstream of Harbor Island and immediately
downstream of Kellogg Island. It is downriver from the Norfolk CSO site, and
was also sampled in 1994 and 1995. PCBs, bis(2-ethylhexyl) phthalates, mercury,
and butyl benzyl phthalates were identified as the primary chemicals of
concern. Seven acres were dredged beginning in November 2003, and capping with
clean material was completed in March 2004. See fact sheet
.
-
Waterfront Recontamination Study. The Panel sponsored a study of Elliott
Bay's central waterfront in 1993 to investigate sources of contamination,
transport and circulation patterns, and depositional rates. See
fact sheet .
-
Elliott Bay Nearshore Substrate Enhancement
Project. In March 1998, four materials (cobble, quarry spall, pea gravel, and
oyster shell) were placed in eight plots to enhance productivity of benthic
infauna, increase distribution of macroalgae, and improve habitat attributes
that support resident and migratory fish species. Monitoring indicated that
macroalgae and sessile invertebrates increased in the plots. Both fish and
epibenthic invertebrates appear to have benefited from this project.
-
Herring's House Park and Intertidal
Habitat Restoration Project (formerly, Seaboard Lumber Site Aquatic Habitat
Project). This project was completed in 2000, except for monitoring which
continues. The work included removal of mill structures, a shoreline dock, and
contaminated sediments. A 1.8 acre intertidal bay was created, with fringing
emergent vegetation in an intertidal zone. Riparian vegetation was also planted
to create a riparian buffer.
-
Hamm Creek Habitat Restoration Project/City
Light North Project. This project is on a 6.2-acres near the Turning Basin No.
3 on the Duwamish Waterway. The project resulted in the creation of two acres
of freshwater marsh, one acre of intertidal estuarine marsh, and 1,900 feet of
new riparian stream bed. The connection to the Duwamish was designed to be
“fish-passable” to allow access to Hamm Creek for salmonid spawning.
-
Turning Basin No. 3. Restoration Project. This
project is located on the former Kenco Marine Services property. An old
building, dock, and grounded barges were removed. Fill material was removed to
push back the shoreline. Marsh and riparian vegetation were planted. The
project was completed in April 2006.
-
North Wind's Weir Restoration Project. This
project is located at Cecil B. Moses Park, upstream of the Turning Basin No. 3.
A one-acre basin was created to provide off-channel habitat for out-migrating
salmonids. Emergent and riparian vegetation was planted.
-
Porter Levee Site. The Porter Levee site is a 30-acre parcel adjacent to
the Green River. The Panel has contributed approximately $390,000 toward
acquisition costs for this property. The U.S. Army Corps (Corps) of Engineers
provided a similar amount under its Section 1135 funding program for
construction activities at the site. In August 1999, the Corps' construction
effort restored the Green River's connection to an isolated channel. This
reconnection provides fish access to an eight-acre side channel and 13 acres of
riparian wetland, and allows for salmon refuge from high flows and
over-wintering habitat for juveniles. This type of habitat is extremely limited
along the middle Green River. See fact sheet .
-
Site 1 The Panel contributed $611,000 toward the purchase of this
property by King County. Working with the Corps, King County will design and
construct more than two acres of off-channel intertidal slough at the critical
transition zone of salt and freshwater mixing.
|
|

|
The Adobe Acrobat Reader is required to view PDF documents.
Click on the Acrobat Reader icon to download the latest version.
|
|
|
|