The U.S.
Environmental Protection Agency (EPA) is the lead agency for cleanup of
the Hudson River PCB Superfund site. EPA and General Electric (GE) estimate
that between 1947 and 1975, from 500,000 to 1.1 million pounds of
polychlorinated biphenyls (PCBs) were discharged from the Fort Edward and
Hudson Falls facilities into the upper Hudson River. An estimated 500,000 to
700,000 pounds of PCBs remain in the river sediments.
In 1991, a subterranean source of PCBs near Baker's Falls, New York, was
identified by GE, EPA, and New York State. This previously unidentified source
was traced to GE's Hudson Falls Plant (Baker's Falls).
Studies of the site conducted in 1993 found pockets of extremely contaminated
groundwater that oozed an oily substance. These "seeps" contained PCB oil in
varying concentrations, ranging from hundreds of parts per million to 90
percent pure PCBs near an old discharge pipe. The studies also identified tons
of heavily contaminated sediment in the raceways of the plant's old mill
building. In June 1994, GE found more seeps of highly concentrated PCB oil in
the river bottom below and next to the mill raceway. The GE Hudson Falls site
is a significant source of PCBs that continues to affect the Hudson River.
In 1984, EPA issued a record of decision (ROD) for a portion of the Hudson River
Superfund site. The ROD called for (1) in-place capping, containment, and
monitoring of remnant deposit sediments; (2) a treatability study to evaluate
the effectiveness of the Waterford Treatment Plant in removing PCBs from Hudson
River water; and (3) an interim no action decision concerning river sediments.
In December 1989, EPA announced that the no-action decision would be
reassessed.
EPA issued a ROD in February 2002, which addressed the risks to people and
ecological receptors associated with PCBs in the sediments of the 40-miles of
the Upper Hudson River. The ROD indicated that PCB contamination in the Hudson
River floodplains would be investigated concurrent with the remedial design
process. In October 2005, EPA took a significant step toward cleaning up PCBs
in the Hudson River by reaching an agreement with GE, requiring it to begin the
dredging called for in EPA’s 2002 ROD. The agreement was published in the
October 13, 2005, Federal Register. The public comment period closed on
December 14, 2005. The Notice of Lodging and Consent Decree are available on
our Case Document page. The Consent Decree formalized
a peer review process to evaluate whether the Engineering Performance Standards
(Residuals, Resuspension, Productivity) could be met individually and
simultaneously. The purpose of the peer review does not include a re-evaluation
of the selected remedy.
Prior to 2002, EPA and GE developed models for the Upper Hudson that predicted
temporal changes in surface sediment concentrations under different remedial
alternatives. Following EPA’s ROD in 2002, over 9000 core samples were
collected from the Upper Hudson during remedial design. The comparison of
predicted and observed surface sediment PCB concentrations suggests that both
models underestimated future PCB concentrations under
natural recovery scenarios, with measured concentrations from 2002-2007
exceeding the upper bound of model predictions for 2003. In addition, PCB
concentrations following the selected remedial alternative estimated from the
recent data are approximately five times higher than EPA model estimates for
River Sections 2 and 3. (Figure 5)
NOAA, NYS Department of State (NYSDEC) and the U.S. Fish and Wildlife Service
(USFWS) identified 57 especially sensitive
or unique habitats (ESUH) in the Upper Hudson River between Fort
Edwards and Troy (Figure 1).
This effort was conducted as part of the consultation process identified in
EPA's 2002 ROD for the Hudson River PCB site. NOAA, NYSDEC and the USFWS have
been working with EPA in an effort to replace and reconstruct especially
sensitive or unique habitats as the Phase 1 and Phase 2 remedies are designed.
In addition, NOAA estimated pre-and post-remedial
sediment PCB concentrations in each ESUH area. Estimated
post-remediation surface and top 2 inches sediment PCBs in River Section 1 ESUH
areas are generally less than 10 ppm and some are approaching 1 ppm
(surface sediments and the top 2 cm slice)
(Figure 5). In contrast, post-remediation PCB concentrations in surface
sediments are expected to exceed 10 ppm in most ESUH areas in River Section 2
(Figure 6) and in the upper two reaches of River Section 3
(Figure 7). These differences in anticipated post-remediation PCB
concentrations are a consequence of a lower cleanup trigger in River
Section 1 than River Sections 2 and 3 but similar sediment PCB concentrations,
at least for River Sections 1 and 2. Few ESUH areas are likely to have post-
remediation concentrations less than 1 ppm PCB based on top slice or surface
PCBs. These findings will be used by the Trustees in the evaluation of residual
injury to natural resources and to identify appropriate on-site and/or off-site
natural resource restoration.
Phase 1 environmental clamshell dredging of PCB-contaminated
sediment was conducted between May 15 and Oct 27, 2009. Approximately 20 tons
of PCBs and 273,600 cy sediment were dredged from ten Certification Units (CUs)
in the Thompson Island Pool. In addition, backfill and caps were installed, as
appropriate to address residual PCBs per the Residual Standard or to sequester
inventory below designed depths of contamination that could not be removed
before the approaching end of the remediation season. Design of the Phase 2
remedy is in progress and could be modified based on the recommendations of the
Phase 1 Engineering Performance Standards peer review panel.
Remedial investigation of the Upper Hudson River
floodplains has also begun. Some properties were sampled by EPA and GE
in 2008 and 2009. Short-term response actions (signage, isolation cover)
designed to protect human health have or will be implemented on a number of
properties.
GE Hudson River Plant Sites
The New York State Department of Environmental Conservation (NYSDEC) is the
support agency for the two GE Hudson River plant sites. NYSDEC issued RODs for
the Ft Edwards plant site in 2002 and the Hudson Falls plant site in March
2004. Remediation has been initiated at both plant sites.
For additional DEC information:
Hudson Falls
Plant Site 
Remedial Work at Hudson Falls and Ft. Edwards Plant Sites